Warning: Technical and possibly boring post. But nonetheless I wanted to document this.
Remodeling HumphreyHouse has presented us with an opportunity to change the air movement in our attic. In order for a good roof to maximize its expected lifetime, and to increase a home's comfort level, it's important to have good ventilation in the attic.
In summer, the underside of a roof collects a ton of radiant heat, as Jay found out first hand this weekend when Chicago was gripped with a heat wave. Without ventilation coming in to move that air up from the underside of the roof to a vent near the peak, the heat has nowhere to go but through the insulation and into the house. Making an attic unbearably hot. During the winter, the heated air from inside the home carries water vapor from laundry, bathrooms, cooking etc. and when the warmer air hits the cold rafters and roof decking, it condenses and can create moisture problems.
Warm air can also cause the snow on top to melt and run down the roof. Now, you may not think this is a bad thing, except when that water runs over a soffit, which is not heated, it will form an ice damn near the end of the roof eave, causing water to refreeze on the shingles and work its way underneath to enter the house. We had some loooong icicles last winter, so hopefully we can avoid them turning into ice damns in the future by increasing ventilation.
However, the problem we're running into is one of headroom. Our rafters are only 2x4s, and we want to get as much insulation as possible without shrinking the room too much. We settled on R19 (2x6) insulation for the sloped part of the ceilings, which requires simply furring down the existing 2x4s. The flat part of the ceiling will have R38 (12 inch) insulation. But this doesn't leave much room for vent chambers - especially the typical foam baffles that you can purchase. These are 2 inches thick, and while we put them under the dormer roof, and will still have plenty of insulation, we won't have much room if we do that in the rest of the attic.
So with our HVAC installer's help, we devised an alternative solution that maximizes our insulation while still creating air chambers for ventilation. We installed a PVC pipe that connects the behind-the-kneewall part of the attic to the peak of the roof, and put a pipe into each rafter bay. In the laundry room, which will generate a lot of moisture, Jay drilled the PVC every few feet to ensure any moisture will get carried away in winter.
But how will the air travel up those pipes to begin with? We plan to install standard 2x4 insulation in the kneewall areas just in case we want warm/semi-heated storage, and to keep extreme weather from coming inside.
So before stapling up that insulation, we furred down the 2x4 rafters behind the kneewall with 1x2's. That would leave a 1" gap for ventilation across the lower part of the roof once the insulation was installed (ice dams, bedamned!) These chambers terminate at a mini-peak at the top of the kneewall to take advantage of existing mushroom vents in the roof, and the PVC is right there to carry the air up to the attic peak where we have more mushroom vents.
So, to make a long story short, our plan is to have sufficient air movement under our roof and above our insulation, which will hopefully keep everything more comfortable and enjoyable.
Tuesday, August 01, 2006
A baffling roof ventilation problem
Posted by
jay
at
5:19 PM
2
comments
Labels: energy efficiency, roof
Tuesday, June 27, 2006
A complete shell

Our dormer is now completely framed - roof and all! We have a torched-down asphalt roof (because the slope is so low), and the sides are, well, sided. We were fortunate with the weather as we only had one slight rainfall. It was actually the morning the roofers were here, but it only interrupted them for an hour.
Over the weekend, Jay's stepdad came over to help install plumbing. Several hours (and plenty of glue sniffing) later, we had about 80% of the plumbing lines that we will need for our new bathroom upstairs.
Some of our initial dormer bathroom layout revolved around where we could run plumbing up and down to the second floor. This week, after a bit of analysis, we realized that there was a large unusable area we could use that was already in place... the back of the narrow closet in the first floor bath! It's 30" deep, but only 18" wide, which means most of the back is too dark and hard to get to anyway.
In addition to housing the drain pipes from above, this will likely be where we run up natural gas and AC lines for the upstairs furnace too. Fitting the pipe into the back turned out to be relatively simple, once we busted through 4" of concrete in the bathroom floors. Talk about a solid foundation for tile!! As John is fond of saying, they just don't build em like they used to!