Monday, May 15, 2006

Time keeps on slippin, slippin, slippin, into the future .....

We finally sat down and did a schedule for the upstairs. The finish date is soooo far away. But at least we're being realistic!
Remember, this is ONLY for the upstairs. I am determined to start the kitchen before the end of the year.
I can't believe I know what we're doing every weekend through the end of October.
We did build a couple of spare weekends in, I think. Not a lot. Erika better have that baby on schedule, that is all I have to say! :)

MAY
May 20 & 21: Siding & Painting Garage
May 27 & 29: Finish Upstairs Demo (sat Frank Tribes show)

JUNE
June 3 & 4: Final Dormer Preparations
June 5-9: DORMER HIRED WORK - framing, cut roof, install skylights/tubes
June 12-26: DORMER HIRED WORK - install flooring, repair roofing
June 17 & 18: Erika's Due Date
June 24 & 25: Nici? And Plumbing .... (John)

JULY
July 1 & 2: Interior Framing for dormer
July 7?: install Heating (Chris)
July 10?: electrical upstairs (Fred)
July 15 & 16: Insulation
July 22 & 23: Drywall
July 29 & 30: Drywall

AUGUST
August 5, 6 & 7: Drywall
vacation!
August 19 & 20: Tile
August 26 & 27: Tile

SEPTEMBER
September 9 & 10: Finish Plumbing, Muddy Buddy Weekend (Jen & Scott to kick some butt)
September 16 & 17: Paint (at long last!)
September 23 & 24: Finish electrical
September 30 & October 1: Flooring

OCTOBER
October 7 & 8: Trim, Frank Lloyd Wright Races
October 14 & 15: Finish the trim!
October 18: We move in, our third anniversary
October 21: Upstairs Halloween Party!